Saturday, December 11, 2010

Dec 11-17



Wednesday, December 8, 2010

Dec 5-10










This week there have been as many as 4 trades on site each day. Electrical has begun the rough in process, HVAC continues to install duct and furnaces, the plumber has continued to work on installing a reserve tank and the water line that will be used to service the trailers for visiting evangelists, and the sprinkler company is still running pipe. On Friday of last week the glass exterior door was installed at the end of the hallway which allows a great deal of natural light into the building. It is very exciting to see all the work moving forward.

The Lord has provided the funds to get the pr
oject to the "roughed in" stage but we still need enough to finish the job. If you know someone who may like to make an end of the year donation for a tax credit please share our need with them. God has used many friends and unexpected avenues to meet our needs thus far and He is due all the glory for what has been accomplished.

Thursday, December 2, 2010

Nov 28 - Dec 4




The heating and air conditioning contractor has been working hard at installing duct and furnaces. While this is a huge job the work is being done diligently and progress is being made each day. The volunteer work force is also completing projects on a steady pace. As you can tell from the pictures young and old alike are getting involved and enjoying the progress.