Monday, November 22, 2010

Nov 14-20




Work continues as the sprinkler contractor installs piping for the sprinkler heads in the first floor classrooms and in the cavity that is between the ceiling and floor. Sheetrock started being put in place in the various mechanical closets to prepare for the HVAC installation that is scheduled to begin next week. What a joy to see God's people working with one another to see the project move forward!